A $6.5 million plan to transform downtown Yellowknife had its first airing in front of councillors on Monday.

Architect Simon Taylor, hired by the city as a consultant, presented plans to turn the disused 50-50 lot – where Franklin Avenue and 50 Street meet – into an open-air plaza.

These are the first fully formed proposals to reach city council since the city bought the lot for $1.45 million late last year. The lot has spent two decades undeveloped, held back by social issues and a lack of downtown investment.

“I’m very impressed and like what I see,” said councillor Cory Vanthuyne of the 65-page document.

“If the momentum created up to today starts to fizzle and fade, I fear it’ll be a very long, hard road to travel to ever bring new life back to the downtown.”

However, some councillors felt the plans did not justify their multi-million dollar price tag.

In full: Plans for transformation of 50-50 lot (pdf, pages 3-163).

The proposed plaza includes a new-look entrance for the adjacent Centre Square Mall, an opportunity for the mall’s stores to make use of the plaza space (for example, outdoor seating for restaurants), and a space for artists to perform or display their work.

Also featured is an ‘iconic’ washroom building and bus stop.

“Instead of sitting here being paralyzed, maybe we should get on with things,” said councillor Dan Wong.

“Homeless people should be welcome in that space, regardless of its purpose. For me, a big part of this project is actually that public washroom – it’s a way we can deal with dignity and basic needs for folks on the street.”

“In very real terms this is a dead portion of the downtown, and it’s been like that for 20 years,” Taylor told councillors.

“Centre Square Mall is very inward looking, typical of malls from 30 years ago. What we propose is to open up the upper mall onto the plaza and then physically modify the plaza somewhat to allow for a mixture of events to occur – you’ll have the potential for social gathering.”

Taylor said concerns about attracting residents to the outdoor plaza in winter were unfounded, citing the example of Edmonton’s Churchill Square, which is used to host events throughout the year.

Councillor Adrian Bell wanted a clear commitment to the project from the two owners of the upper and lower mall, both of which recently changed hands, before proceeding. However, Taylor said the city had to take the first step.

“The previous mall owners hadn’t spent dollar one since 1989,” said Bell. “Having this new [upper mall owner] on board is very interesting, but there’s a big difference between someone on the phone saying they’re very interested, and seeing dollars committed.”

“They have also seen the city saying ‘we’re going to do a bunch of things’ for some time, and nothing has happened,” replied Taylor.

“They are keen to see the city step forward and start to organize this. The city has to say it’s going to go into that next step. The [owners] are going to be there. They have identified that. It’s really the nitty-gritty of how much they’re going to do.”

Schematic of Yellowknife 50-50 lot plan
This schematic shows how the 50-50 lot (bottom left) and the adjacent mall would change.

The full plans call for the public washroom and bus shelter building to become a “landmark and architectural element, signifying the downtown core … acting as a sort of billboard to the downtown”.

The washrooms would be predominantly transparent and kept at a relatively low temperature, to discourage anyone from staying inside the building for lengthy periods of time.

Longer-term – and beyond the scope of this stage of the downtown revitalization – there is the suggestion that a new library could be built in the area, alongside other public services.

Councillor Rebecca Alty questioned, given high levels of support for a library in the public engagement process, why no library was included in the immediate plan put forward on Monday.

Alty also felt the 50-50 lot proposals would create an open-air plaza that competes unnecessarily with the Somba K’e civic plaza, without being able to hold as many people.

The city believes it currently has just over $1 million in capital budget funding for this project, alongside six-figure sums from the CanNor development agency and a separate downtown reserve fund.

Administration wants to find more funding avenues internally, but also notes that its plans will require “significant investment” from the two mall owners. For the moment, there is no set date for the completion of transformation work on the lot.

“Further commitment is essential,” urged a review of the proposals prepared by city administration. “The next step of capital investment is required if the condition of downtown Yellowknife is to improve.

“Without this commitment, no tangible social, economic or physical progress will have been made over the past decade.”

The plans will be brought to a full council session next week.

Artist's impression of Yellowknife 50-50 lot plan
A guide to new features proposed at the 50-50 lot.
Artist's impression of Yellowknife 50-50 lot plan
An artist’s impression of how part of the transformed lot may appear.
Ollie Williams
Ollie Williams
Hello! I'm the one with the British accent. Thanks for supporting CJCD. To contact me, you can email me, find me on Twitter or call (867) 920-4663.

Continue Reading

You may also like



cjcd Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

“Place branding” pitched to Yellowknife city council

Economic Development Director Kerry Thistle and Community Engagement Advisor Richela Solatorio presented what is described as a “master story” of the city through the experiences of those who live here. While some aspects of the planned pitch were met with enthusiasm, city council members said that Indigenous identity and culture must be integral to such a project.

Fort Smith RCMP investigate fatal snowmobile crash

Fort Smith RCMP are investigating a fatal snowmobile collision that occurred in a remote wilderness area that occurred over the weekend

Sambaa K’e Access Rd Closes for season, with more roads on closure notice

GNWT’s Department of Infrastructure says Sambaa K'e Access Road has been closed for the season and more sections of the Mackenzie Valley Winter road on closure notice. The department closed the Mackenzie Valley Winter Road's Wrigley – Délı̨nę Junction. Today, all remaining sections of the Mackenzie Valley Winter Road were placed on 24-hour closure notice. Wekweètì and Gamètì winter roads are currently restricted to night travel only between 10 pm to 10 am.

GNWT releases Tourism 2030 strategy

The Government of the Northwest Territories has released Tourism 2030: Sustainable Journeys Ahead, a new five-year strategy to help grow and support the territory’s tourism sector.

GNWT apologizes for 2022 raid of Lutselk’e cultural camp

GNWT issued an apology on behalf of the territorial government to the Lutselk'e Dene First Nation for a raid at a camp at Artillery Lake back in 2022. Simpson said that a review of the conduct of wildlife officers is ongoing. Four years ago, the community was subject to what Elders and community members described as a "traumatic" raid by wildlife officers for allegedly harvesting caribou considered off limits in the zone. The search warrant was later deemed unlawful in N.W.T.’s superior court.